Factory Registration / Establishment License

Registration of a factory or establishment with the Department of Inspection for Factories and Establishments.

Last verified 1 September 2026 by legal-reviewer · Methodology · Always confirm with the issuing authority before acting.

Issuing Authority
Department of Inspection for Factories and Establishments (DIFE)
Processing Time
15 working days
Complexity
Moderate
Renewal Cycle
Every 12 months

Who needs this

Factories and establishments covered by Bangladesh Labour Act 2006.

When it becomes required

Within 30 days of commencing operations, for covered establishments.

Legal basis

The Bangladesh Labour Act 2006

Relevant industries

  • Garments & Textiles
  • Manufacturing

Required documents

0 of 4 ready
  • Trade Licence

    Local government licence.

    Mandatory
  • Factory layout + Machinery list

    Premises and equipment details.

    Mandatory
  • Fire + ECC (if required)

    Safety/environmental where applicable.

    Conditional
  • NID + Incorporation (if company)

    Identity and entity proof.

    Mandatory

Tick each document as you collect it — progress for this licence is saved in your browser only. We never receive it.

Process

  1. Prepare factory layout

    Draw premises and machinery plan.

  2. Apply to DIFE

    File with trade licence, layout and fee.

  3. Inspection

    DIFE officer inspects workplace and safety.

  4. Collect registration

    Receive Factory Registration Certificate.

Fees and timeline

All amounts in BDT unless noted. Verified figures are dated; always confirm before paying.

Government fee BDT 2,000 – 10,000 Scaled by factory size per DIFE schedule.
Professional assistance Request a quote → We scope government fees, VAT, stamp and other costs for your case — no public price list.
VAT No VAT on government fee — check current NBR rules. No VAT on registration.
Stamp / duty BDT 1,000 Affidavit stamp.
Other fees BDT 1,000 – 3,000 Trade licence, fire, ECC where applicable.
Total estimated BDT 4,000 – 14,000 Sum of government + stamp + other (ex-VAT, ex-professional). Ask for a formal quote.
Processing time 15 working days (official) 15 official days; 15–30 observed.
Renewal Renew every 12 months. Renew annually.

Common mistakes

No fire/ECC where required, missing worker register, premises not inspected.

Frequently asked questions

When must I register a factory?

Within 30 days of commencing operations for covered establishments.

What is the fee?

BDT 2,000–10,000 government fee plus professional assistance.

Does a factory need ECC and fire?

Conditional — depends on size, Red/Orange category and occupancy.